The Nine Stages
Every stage has a defined output document, so at any point you can see what has been signed off and what is pending.
| # | Stage | Output | Typical duration |
|---|---|---|---|
| 1 | Site survey & requirement capture | Measured drawing, ambient light readings, viewing-distance map | 1 day |
| 2 | Design & BOQ | Pitch, cabinet layout, controller, power and BOQ | 2–3 days |
| 3 | Structural design | Wall/steel frame drawings, load calculation, fixing schedule | 2–4 days |
| 4 | Electrical & MEP coordination | Dedicated circuits, earthing, cable-tray routes, UPS/redundancy plan | Parallel with 3 |
| 5 | Supply | Cabinets, controller, spares delivered and inspected | 3–5 weeks |
| 6 | Structure & mounting | Frame erected, laser-levelled, cabinets hung | 1–3 days |
| 7 | Cabling & mapping | Power/data cabling, receiving-card mapping, sending-card config | 1 day |
| 8 | Calibration & testing | Brightness/colour calibration, dead-pixel scan, burn-in test | 1 day |
| 9 | Handover & training | As-built documents, CMS training, warranty and AMC start | Half day |